|
Resources
Main Menu
|
 |
 |
|
|
This Week's Question
June
28, 2004
By Nena Groskind |
 |

Q: I
am a new landlord with a not so unusual property owner-tenant dispute.
My tenant inquired about the possibility of making some improvements
to his apartment. I agreed that the work would improve the property,
and said I was willing to do it, but I told them the work would
require a long weekend, during which the room in question would have
to be vacant. In further discussions, I suggested that I expand the
scope of the project to include work on another room and the tenants
agreed enthusiastically to that idea. I then drew up a work schedule,
pointing out that the project now would require more than the long
weekend, and also noting that the I couldn’t give them a precise
estimate of the time required, because there was no way to predict
what we would find behind some wall covering we were planning to
remove.
As it turned out, the walls were in worse shape than we thought, and
the work required one day longer than I had projected – we finished
the “messy” part of the project on Tuesday instead of Monday. And on
one of those days, the tenants returned to find the room in less than
desirable condition. Although the room was essentially habitable, they
stayed with friends that night. Once the first phase was completed, I
was able to schedule the subcontractors to do the finish work. I had
arranged originally for them to come on Thursday, two days after the
initial work was finished. But the tenants asked for a delay because
of their work schedule; I agreed, but pointed out that rescheduling
the first subcontractor also would require rescheduling the second
one. The net effect was to extend the project by about two weeks. I
didn’t think much about it at the time, because the apartment was
basically in a habitable condition.
I came by the apartment every day while the work was in progress to do
extra clean-up, check on the progress, and make sure the tenants
weren’t being inconvenienced unnecessarily. They never indicated that
there was any problem, except for the one evening when they spent the
night with friends. But at the beginning of the next month, they
informed me that they were withholding $500 in rent, because the
project took longer than I had estimated. I pointed out that the
project stuck pretty much to the schedule I had outlined; the major
delay resulted from their request that I reschedule a subcontractor. I
truly felt I had adhered to both the letter and the spirit of the
agreement, but their dissatisfaction was genuine, so I proposed
rebating $150 of the month’s rent, to compensate them for their
inconvenience. They said they would settle for $400, which I said was
unacceptable. That’s where we left it. My plan now is to deduct the
outstanding rent from their security deposit at the end of the lease.
Is that a legally justifiable position? I’d appreciate your input as a
neutral third party.
|
A: I
usually do try to maintain some level of neutrality; but in this case,
I confess, I’m inclined to support your position. This looks like a
classic illustration of a lesson many landlords learn the hard way:
“No good deed goes unpunished.”
Your tenants undoubtedly have a different view of the circumstances,
and I’m only hearing your side of the dispute, but it appears from
your description that you agreed to make some totally voluntary
improvements in the property, encountered problems that are typical of
any construction project, and did everything you could to minimize the
inconvenience to your tenants. They repaid you by using a relatively
minor delay as an excuse for withholding a large chunk of their rent.
Presumably, this will make you think twice about entering into a
similar voluntary arrangement with other tenants in the future. It
might even make you think twice about whether you want to be a
landlord at all.
Your objection to your tenants’ decision to withhold a portion of
their rent is understandable; I suspect that no jury of your peers
would disagree with you. But deducting the amount in dispute from the
security deposit at the end of the tenants’ lease may not be the best
strategy, the attorneys I consulted suggested. The security deposit
statute allows landlords to deduct from the deposit “unpaid rent that
was not validly withheld or deducted.” If you make that deduction,
your tenants, presumably, will claim that their withholding was
justified. While judges probably wouldn’t, and arguably shouldn’t,
give tenants that much leeway, you can’t predict what any given judge
might do. And if the decision went against you, you be liable for up
to triple their damages, plus attorneys’ fees.
Another, probably safer option is to go act now and move to evict your
tenants for nonpayment of rent. Either way, you and your tenants are
probably are going to end up fighting in court over whether their rent
withholding was legal; the only questions are when that battle will
occur and what the stakes are going to be. By waiting until the end of
the lease to press your claim, you’re just postponing the inevitable.
And by fighting over the security deposit rather than over the
eviction, you incur a far greater down side risk if you lose. Lose on
the security deposit, and you could be out triple damages plus
attorneys' fees. Lose on the eviction, and you’ll lose the
satisfaction of telling your tenants now that they will have to find
somewhere else to live; you’ll have to wait until the current lease
expires to deliver that message.
|
|